试题查看

首页 > PMP考试 > 试题查看
【单选题】

In your project, you have reason to believe that the current variances occurred because of extraneous factors, and you do not expect similar variances to happen in the future. What should be the estimate at complete for your projectBAC=$300,000,AC=$100,000,EV=$150,000,CPI=$1.5.

A、$250,000.
B、$220,000.
C、$280,000.
D、$200,000.
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

54%的考友选择了A选项

14%的考友选择了B选项

18%的考友选择了C选项

14%的考友选择了D选项