While completing a project a project manager realizes be needs to decrease project costs.After researching his options, he comes up with the following choices. Which choice wouldDECREAS

E、project costs
A、Change to component
A、from componentB、Component
A、costs more to purchase but has a lower life cycle cost thanB、
B、Change task
A、to be completed by resourceB、instead of ResourceC, ResourceB、is a more experienced worker.
C、Move tasksB、and H to occur concurrently, and take the risk of a 30% increase in the need for five more resources later.
D、Remove a test from the project plan.
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

13%的考友选择了A选项

15%的考友选择了B选项

8%的考友选择了C选项

64%的考友选择了D选项