【单选题】

At XYZ InC、, the hourly wage for semi-skilled workers is $14.00. The annual audit shows that fringe benefits cost 30%of basic wages, and that overhead costs are 60% of wages plus fringe benefits. What is the “loaded” hourly wage for a semi-skilled worker at XYZ InC、

A、$27.14.
B.$28.96.
C.$30.03.
D.$29.12.