【单选题】

In risk response planning,you are in the process of developing options,and determining actions to reduce threats to your project’s objectives.When you show the results of your risk response planning to your project sponsor,she is not comfortable with the risks in the project and she suggests that the project scope should be decreaseD、This is an example of______.

A、inappropriate risk management because it is having a direct impact on your project scope
B.risk avoidance
C.risk mitigation
D.risk transfer
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

14%的考友选择了A选项

85%的考友选择了B选项

0%的考友选择了C选项

1%的考友选择了D选项