【单选题】

You are in the development phase of a software project and meeting the development team to collect the status.You want to show the team members the actual dependencies of different tasks.Which scheduling tool you will be using to explain them(choose the best answer)

A、Milestone char
B.Flow char
C.Network diagra
D.Gantt char
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

0%的考友选择了A选项

23%的考友选择了B选项

70%的考友选择了C选项

7%的考友选择了D选项