试题查看

首页 > PMP考试 > 试题查看
【单选题】

You are the project manager for software development project.The feasibility study can start any time and takes 1 week and requirement gathering takes 2 weeks which can start only after feasibility study.The design and test plan development can start in parallel after the requirements gathering.Test plan preparation takes 8 weeks followed by a review by the customer and the time estimated for review is 1 week.After the review,Test data preparation takes 6 weeks.Design takes 6 weeks and it is followed by development and unit testing,for one module it takes 2 weeks and for the other module it takes 2 weeks.There are no dependencies between modules and they can be developed simultaneously.After test data preparation and development and unit testing of both the modules,there is 2 weeks system testing.What is duration of the critical path

A、14 week
B.15 week
C.20 week
D.19 week
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

0%的考友选择了A选项

23%的考友选择了B选项

70%的考友选择了C选项

7%的考友选择了D选项

你可能感兴趣的试题