【单选题】

You are managing tooling for an aircraft part.Your team members tell you that they found a few defective parts.When you asked them the reasons for the defect,they mentioned that it could because of several reasons including the material used,the measurement system,inaccurate tolerances in the machine or other factors.To help them to illustrate better how various factors might have contributed to the defect,you will______.

A、use a control chart
B.create a flowchart
C.draw a fishbone diagram
D.draw a Pareto chart
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

2%的考友选择了A选项

34%的考友选择了B选项

59%的考友选择了C选项

5%的考友选择了D选项