You are working on internal projects for a big corporation.You are in to requirement definition for new claim system that will enable employees claim their hours worked on the projects using their mobile phones also.Due to budget cuts it was decided to cancel the project and deploy the people to commercial projects.Which of the following is true

A、The project ended due to integration because the resources where distributed to commercial projects。
B.The project ended due to starvation because the funding was cu
C.The project ended due extinction because of the budget cut。
D.The project ended due to integration because of budget cu