监理工程师习题练习

监理工程师考试每日一练(2019/6/15)
1题:施工合同示范文本中规定的固定价格合同()。
A.是在约定的风险范围内价款不再调整的合同
D.是绝对不可调整合同价款的一种计价方式
C.是约定范围内的风险由承包人承担
D.包括工程承包活动中采用的总价合同和单价合同
E.无需约定风险范围
【多选题】:        

2题:Personal firewall is a technology that helps (66) intruders from accessing data on your PC、via the Internet or another network, by keeping (67) data from entering or exiting your system.
Hackers do not just target national security organizations for (68) : They want your tax returns, network passwords, or bank account numbers.And you do not want the FBI kicking in your door because someone hijacked your PC、to (69) in the latest denial-of-service attack on the Internet. Now that "always-on" broadband connections such as cable modems and digital subscriber line are becoming more popular, home users are at risk. Fortunately, you can protect your datA、Firewalls can block (70) attacks and protect your PC、from outside threats.
A.enlist

B、go to
C.participate
D.attach
【单选题】:      

3题:项目建议书是拟建项目单位向国家提出的要求建设某一项目的建议文件,是( )。
A.对工程项目建设的轮廓设想
B.为项目投资决策提供依据
C.对项目建成后的经济效益的预测
D.建设工程的决定性环节
【单选题】:      

4题:凡是具有独立的设计文件,竣工后可以独立发挥生产能力或工程效益的工程为( )工程。
A.建设
B.单项
C.单位
D.分部分项
【单选题】:      

5题:关于建设项目环境管理提出的“三同时”要求,是指环境治理设施与项目主体工程必须()。
A.同时开工、同时竣工、同时投产使用
B.同时设计、同时施工、同时投产使用
C.同时开工、同时竣工、同时验收
D.同时设计、同时开工、同时验收
【单选题】:      

6题:对工程进度造成影响的因素中,属于业主因素的有(  )。
A.不能及时向施工承包单位付款
B.不明的水文气象条件
C.施工安全措施不当
D.不能及时提供施工场地条件
E.临时停水、停电、断路
【多选题】:        

7题:对于企业不使用政府资金投资建设的项目,一律不再实行( )。
A.登记制
B.审批制
C.核准制
D.备案制
【单选题】:      

8题:在工程网络计划中,判别关键工作的条件是该工作( )。
A.结束时间与紧后工作开始之间的时距最小
B.开始时间与其紧前工作之间的时间间隔为零
C.结束时间与其紧后工作之间的时间间隔为零
D.最迟开始时间与最早开始时间的差值最小
【单选题】:      

9题:当工作在不同单位时间里的进展速度不相等时,累计完成的任务量与时间的关系就不可能是线性的,此时应采用()比较法进行工作实际进度与计划进度的比较。
A.匀速进展横道图
B、列表
C、非匀速进展横道
D、S曲线
【单选题】:      

10题:债权人的撤销权自债权人知道或应当知道撤销事由之日起( )年内行使。
A.1
B.2
C.3
D.5
【单选题】:      

 