A project manager believes that modifying the scope of the project may provide added value
for the customer. The project manager should:
A Change the scope baseline
B Prepare a variance report
C Call a meeting of the configuration control board
D Change the project’s objectives
E Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
试题出处:http://www.examtiku.com/shiti/8778829587.html
网考网参考答案:E
网考网解析:进入考试题库查看解析
大数据分析:根据网考网与考试题库的统计分析,该试题:
16%的考友选择了A选项
83%的考友选择了B选项
0%的考友选择了C选项
0%的考友选择了D选项
1%的考友选择了E选项
考友解析与评论:
· 这个答案应该是错的,应该是E
· 这个答案与百度百科里面的内容不符合
· 这个答案应该是错误的