试题来源:2012年pmp考试模拟试题及答案(四)
Increasing resources on the critical path activities may not always shorten the length of the project because:
A Certain activities are time-dependent rather than resource-dependent (i.e., using three ovens rather than one to bake a cake).
B Safety, OSHA and EPA may have placed restrictions on the number of people used on certain activities or in the physical location of the project.
C The skill level of the added resources might not be appropriate for the activities to be performed.
D Adding more resources may create additional work and produce inefficiencies (i.e., additional people may need training and supervision.)
E All of the above.
试题出处:http://www.examtiku.com/shiti/8846222469.html
网考网参考答案:E
网考网解析:进入考试题库查看解析
大数据分析:根据网考网与考试题库的统计分析,该试题:
28%的考友选择了A选项
0%的考友选择了B选项
6%的考友选择了C选项
0%的考友选择了D选项
66%的考友选择了E选项
考友解析与评论:
· 这个答案肯定不对
· 这题错在哪里?
· 同样的题比原先难了
发布评论 查看全部评论