 You are managing an internal

2014年11月29日来源:PMP考试 所有评论

试题来源:PMP认证考试练习题及参考答案(九)
 You are managing an internal project where a vice president from the user group is acting as the sponsor. You have just been informed by your team that the critical path has slipped by three weeks. You should:
A Immediately inform the sponsor and ask for advice
B Do nothing until the slippage occurs
C See the sponsor after you have evaluated alternatives, recommendations, and performed an impact analysis
D Look for someone to blame before you see the sponsor
E Inform your senior management of the problem and tell them that you will get back to them after you assessed the situation

试题出处:http://www.examtiku.com/shiti/958318893.html
网考网参考答案:C
网考网解析:
进入考试题库查看解析
大数据分析:根据网考网与考试题库的统计分析,该试题:
85%的考友选择了A选项
6%的考友选择了B选项
5%的考友选择了C选项
0%的考友选择了D选项
4%的考友选择了E选项
考友解析与评论:
 · 我也是C,是不是标准答案,晕
 · 这个答案与百度百科里面的内容不符合