根据网考网和考试题库的统计分析,以下试题在2014-11-28日PMP选择题习题练习中,答错率较高,为:49%
a task-oriented family tree of activities is a:
a. detailed plan.
b. linear responsibility chart.
c. work breakdown structure.
d. cost account coding system.
e. work package description.
参考答案:C,答错率:49%