试题来源:2014年pmp考试模拟试题及答案(三)
You are managing an internal project where a vice president from the user group is acting
as the sponsor. You have just been informed by your team that the critical path has slipped by
three weeks. You should:
A Immediately inform the sponsor and ask for advice
B Do nothing until the slippage occurs
C See the sponsor after you have evaluated alternatives, recommendations, and performed an
impact analysis
D Look for someone to blame before you see the sponsor
E Inform your senior management of the problem and tell them that you will get back to them
after you assessed the situation
试题出处:http://www.examtiku.com/shiti/879303226.html
网考网参考答案:C
网考网解析:进入考试题库查看解析
大数据分析:根据网考网与考试题库的统计分析,该试题:
60%的考友选择了A选项
12%的考友选择了B选项
18%的考友选择了C选项
10%的考友选择了D选项
考友解析与评论:
· 这个题,确定是C了?
· 有歧义的题
· 我做了好几遍答案都是C
发布评论 查看全部评论