PMP考试

Problems can occur in properly defi

2014年12月01日来源:PMP考试 所有评论

试题来源:PMP认证考试练习题及参考答案(九)
Problems can occur in properly defining a project because: 
A Project goals may not be agreeable to all parties 
B The plan was "too loose," thus allowing priorities to change 
C Low turnover of project personnel 
D Too much communication between the client and project personnel 
E The project objectives were quantified 


试题出处:http://www.examtiku.com/shiti/9552322315.html
网考网参考答案:A
网考网解析:
进入考试题库查看解析
大数据分析:根据网考网与考试题库的统计分析,该试题:
80%的考友选择了A选项
11%的考友选择了B选项
2%的考友选择了C选项
3%的考友选择了D选项
4%的考友选择了E选项
考友解析与评论:
 · 原先有道题和这题几乎一样,只是稍有不同,大家看看就可理解了,那个答案正确。
 · 这个答案肯定不对
 · 为什么选这个,有没有大神解答一下

发布评论 查看全部评论

相关推荐