根据网考网和考试题库的统计分析,以下试题在2014-12-1日PMP选择题习题练习中,答错率较高,为:93%
Resource leveling _____.
A Allocates resources to activities to find shortest schedule within fixed resource limits.
B Smoothes out resource requirements by rescheduling activities within their float time.
C Smooths out resource requirements by substituting activities with unassigned resources.
D Attempts to reduce resource requirements within a constraint on project duration
E B or D
参考答案:E,答错率:93%
查看解析:进入考试题库查看解析