根据网考网和考试题库的统计分析,以下试题在2014-12-9日PMP选择题习题练习中,答错率较高,为:99%
【单选题】perhaps the biggest problem facing the project manager during integration activities within a matrix structure is:
a. coping with employees who report to multiple bosses
b. too much sponsorship involvement
c. unclear functional understanding of the technical requirements
d. escalating project costs
e. all of the above
网考网参考答案:A,答错率:99%