根据网考网和考试题库的统计分析,以下试题在2014-12-24日PMP选择题习题练习中,答错率较高,为:63%
【单选题】 Project trade-offs vary between
A risk, cost and schedule.
B direct cost, indirect cost, and resource availability
C quality, schedule and time
D cost, quality and schedule
E contract terms, scope and budget
网考网参考答案:D,答错率:63%