【单选题】The scope of a project can be expected to change if: 
A The project manager must provide cost estimates without having a design concept 
B Oversimplification (underestimating) of the nature of the work occurs 
C The project manager is assigned after the project is defined, and the cost and schedule are approved 
D A clear objective is not provided 
E All of the above are possible based upon the situation 


网考网参考答案:E,答错率:90%