【单选题】Free float is the amount of time that an activity may be delayed with out affecting the _____.
A Early start of the succeeding activities.
B Late start of the succeeding activities.
C Project finish.
D Cost of the project.
E None of the above.
网考网参考答案:A,答错率:74%