根据网考网考试中心的统计分析,以下试题在2015-1-22日PMP选择题习题练习中,答错率较高,为:30%
【单选题】make or buy decisions are usually made during the _____ phase of a project.
a. conceptual
b. development.
c. implementation
d. execution
e. close-out
网考网参考答案:B,答错率:30%
试题解析:点击查看解析