根据网考网考试中心的统计分析,以下试题在2015-12-6日PMP考试选择题习题练习中,答错率较高,为:99%
【单选题】the critical path in a schedule network is the path that:
a. takes the longest time to complete
b. must be done before any other tasks
c. allows some flexibility in scheduling a start time.
d. is not affected by schedule slippage
e. all of the above.
网考网参考答案:A,答错率:99%
试题解析:点击查看解析