【单选题】in performing an impact analysis, the most effective tool to ensure all risks are identified on large projects is the:
a. work breakdown structure
b. milestone review and schedule technique
c. cost/schedule control system
d. planning programming budget system
e. program and evaluation review technique
网考网参考答案:A,答错率:80%
试题解析:点击查看解析