PMP考试

易错题:in performing an impact analysis, t

2015年12月15日来源:PMP考试 所有评论

根据网考网考试中心的统计分析,以下试题在2015-12-14日PMP考试选择题习题练习中,答错率较高,为:80%
【单选题】in performing an impact analysis, the most effective tool to ensure all risks are identified on large projects is the:
a. work breakdown structure
b. milestone review and schedule technique
c. cost/schedule control system
d. planning programming budget system
e. program and evaluation review technique

网考网参考答案:A,答错率:80%
试题解析:
点击查看解析

发布评论 查看全部评论

相关推荐