【单选题】one of your project team members has made a technological breakthrough on an r & d project. the result will be new business for the
company, as well as a company patent. the team member received a company bonus. the motivational strategy used here is:
a. job enrichment
b. linking pay and performance
c. behavior modification
d. freedom in the work place
e. all of the above
网考网参考答案:B,答错率:58%