PMP习题练习

PMP考试易错题(2017/9/1)
1题:在开始执行项目费用管理的3 个过程工作前,还有一个由项目管理团队完成的规划过程在制定项目管理计划中编制,是:
A、活动费用估算
B、成本管理计划
C、项目资金要求
D、成本预算计划
【单选题】:      

2题:The use of the project reports: 
A are not necessary on small projects 
B provides a means whereby various levels of authority can judge project performance 
C provides insight into project areas and the effectiveness of the control systems 
D All of the above 
E B and C 
【单选题】:        

3题: Contract closure procedure and administrative closure procedure have several common characteristics,the following are their common characteristics except______.
A.exit criteria
B.contract term
C.step-by-step
D.activities and responsibilities
【单选题】:      

4题:担保成本是以下哪种成本的范例?
A、内部失败成本
B、评估成本
C、外部失败成本
D、客户满意成本
【单选题】:      

5题: A paint manufacturer authorizing a project to establish guidelines to handle toxic material is an example of a project initiate because of______.
A.market demand
B.a customer request
C.a leagal requirement
D.a technological advance
【单选题】:      

 

您正在结束答题

请确认是否提交试卷?

继续做题 确认提交