根据网考网考试中心的统计分析,以下试题在2017/10/16日PMP考试习题练习中,答错率较高,为:89%
【单选题】Scheduling systems such as PERT, ADM, and PDM are project management tools to be used by:
A The project manager and project office personnel.
B The project team and functional managers.
C The project sponsor.
D All of the above.
E A and B only.
网考网参考答案:E,答错率:89%