第1题:项目定义专题会参加者不包括( )。 A.项目发起人和项目推动者 B.项目设计阶段和实施阶段的管理者 C.关键的职能经理 D.所有施工人员 |
【单选题】: |
第2题:在弱矩阵组织中,项目经理的角色是: A. 协调员和联络员 B. 有相当权力的项目经理 C. 支持性人员 D. 职能经理 |
【单选题】: |
第3题:the type of contract (payment mechanism) chosen for a project is often a reflection of the degree of risk associated with completing that project. for a firm fixed price contract, payment for risk _____ . a. is accomplished by paying the actual costs to the contractor. b. is accomplished by paying the contractor for his costs plus a fixed fee (profit). c. is an undisclosed contingency in the contractor's bid. d. is accomplished by paying for the budgeted costs of dealing with risks, as predicted in the project risk assessment. e. b and c |
【单选题】: |
第4题:为提高PMI 的权威性,应当遵守: A、PMI 道德规范 B、PMI 成员道德规范 C、PMP 道德规范 D、PMBOK 规定的道德规范 |
【单选题】: |
第5题:关于概率和影响矩阵,下列哪个说法是正确的? A.对机会而言,高风险(黑灰色)区域意味着代表最大的利益 B.对机会而言,低风险(中灰色)区域意味着最低的风险和最好的利益 C.对风险而言,高风险(黑灰色)区域意味着最大的利益 D.对风险而言,低风险(中灰色)区域应该必须首先确定 |
【单选题】: |