根据网考网考试中心的统计分析,以下试题在2017/10/24日PMP考试习题练习中,答错率较高,为:86%
【单选题】Once the logic of a network is laid out, the project manager will conduct a forward pass and backward pass through the network. This will provide information on the _____ and identification of the _____ .
A Slack for each activity, critical path.
B Slack for each activity, high risk activities.
C Manpower shortages, high risk activities.
D High risk activities, non-critical paths.
E Manpower availability, contingency plans.
网考网参考答案:A,答错率:86%