根据网考网考试中心的统计分析,以下试题在2017/11/1日PMP考试习题练习中,答错率较高,为:35%
【单选题】The monthly report to the client shows zero schedule variance. However, members of the team know that a milestone has been missed that will cause an overall delay to the project. Which one of the following is being inadequately reported?
A.Communication plan variance
B.Resource management plan
C.Critical path status
D.Risk analysis
网考网参考答案:C,答错率:35%