PMP习题练习

PMP考试易错题(2017/11/2)
1题:Problems can occur in properly defining a project because: 
A Project goals may not be agreeable to all parties 
B The plan was "too loose," thus allowing priorities to change 
C Low turnover of project personnel 
D Too much communication between the client and project personnel 
E The project objectives were quantified
【单选题】:        

2题:属于非经营性项目的是( )。 
A 石油化工项目    
B 环境保护项目     
C 钢铁项目     
D社会公益事业项目     
E  某些公用基础设施项目
【多选题】:        

3题:与潜在供货商开会,确保任何投标人都不会受到特殊待遇,让所有人对采购具有明确、 共同的理解,这个会议称作下列哪一项?
A. 卖方-投标人会议
B. 投标人会议
C. 采购谈判会议
D. 卖方会议
【多选题】:      

4题:项目可行性方案的类型按照相互之间的关系可以分为( )。 
A.独立型 
B.混合型
C.互补型 
D.互斥型
E.层次型
【多选题】:        

5题:The monthly report to the client shows zero schedule variance. However, members of the team know that a milestone has been missed that will cause an overall delay to the project. Which one of the following is being inadequately reported?
A.Communication plan variance 
B.Resource management plan
C.Critical path status
D.Risk analysis
【单选题】:      

 

您正在结束答题

请确认是否提交试卷?

继续做题 确认提交