根据网考网考试中心的统计分析,以下试题在2017/11/12日PMP考试习题练习中,答错率较高,为:95%
【单选题】The scope of a project can be expected to change if:
A The project manager must provide cost estimates without having a design concept
B Oversimplification (underestimating) of the nature of the work occurs
C The project manager is assigned after the project is defined, and the cost and schedule are approved
D A clear objective is not provided
E All of the above are possible based upon the situation
网考网参考答案:E,答错率:95%