根据网考网考试中心的统计分析,以下试题在2017/11/19日PMP考试习题练习中,答错率较高,为:44%
【单选题】The critical path in a schedule network is the path that:
A Takes the longest time to complete
B Must be done before any other tasks
C Allows some flexibility in scheduling a start time.
D Is not affected by schedule slippage
E All of the above.
网考网参考答案:A,答错率:44%