根据网考网考试中心的统计分析,以下试题在2017/11/22日PMP考试习题练习中,答错率较高,为:95%
【单选题】The range of time allowed for an activity to be completed in is the _____.
A Planned time (Duration).
B Float time (LS - ES, or LF - EF).
C Critical time (when ES = LS, or EF = LF).
D Scheduled time (LF - ES).
E Event.
网考网参考答案:D,答错率:95%