PMP考试

易错题:a non-critical path activity is com

2017年11月25日来源:PMP考试 所有评论

根据网考网考试中心的统计分析,以下试题在2017/11/24日PMP考试习题练习中,答错率较高,为:38%
【单选题】a non-critical path activity is completed in half the time. then,
a. the critical path is also reduced.
b. the slack in the path containing this activity will increase.
c. the total cost for this activity has decreased.
d. manpower from this activity can be assigned to other activities.
e. all of the above.

网考网参考答案:B,答错率:38%
网考网试题解析:

暂时没有解析查看试题解析出处>>