【单选题】project life cycles provide a better means of measurement of progress and control. the four phases of a project are conceptual development,
_____, _____, and _____.
a. preliminary planning, detail planning, closeout
b. implementation, reporting, termination
c. development, implementation, termination
d. execution, reporting, finishing
e. implementation, termination, post-audit review

网考网参考答案:C,答错率:73%