【单选题】The critical path is calculated by 
A subtracting the end date of task one from the start date of task two. 
B determining which tasks have the least amount of total slack. 
C totaling the time for all activities. 
D determining the shortest path through the network. 
E Determining which tasks have the most slack 

网考网参考答案:B,答错率:67%