PMP考试

易错题:During the planning phase of a proj

2018年04月24日来源:PMP考试 所有评论

根据网考网考试中心的统计分析,以下试题在2018/4/23日PMP考试习题练习中,答错率较高,为:47%
【单选题】During the planning phase of a project, you realize that more than one functional department possesses the skill and technical know-how to perform a given task. The best way for the project manager to handle this would be to: 
A Make the decision, document it in the linear responsibility chart, and distribute the chart to all departments. 
B Let the affected line groups decide among themselves who will perform the work 
C Ask the executive sponsor to make the decision 
D Allow each line group to perform part of the task 
E All of the above 

网考网参考答案:B,答错率:47%
网考网试题解析:

暂时没有解析查看试题解析出处>>

发布评论 查看全部评论

相关推荐