根据网考网考试中心的统计分析,以下试题在2018/4/23日PMP考试习题练习中,答错率较高,为:47%
【单选题】During the planning phase of a project, you realize that more than one functional department possesses the skill and technical know-how to perform a given task. The best way for the project manager to handle this would be to:
A Make the decision, document it in the linear responsibility chart, and distribute the chart to all departments.
B Let the affected line groups decide among themselves who will perform the work
C Ask the executive sponsor to make the decision
D Allow each line group to perform part of the task
E All of the above
网考网参考答案:B,答错率:47%