PMP习题练习

PMP考试易错题(2018/5/21)
1题:Overlapping activities on a project, such as design and construction, is referred to as: 
A Fast tracking 
B Risk conversion. 
C Parallel management. 
D Process improvement. 
E Synchronous manufacturing 
【单选题】:        

2题:你已经对项目时间表提出乐几项修改。在某些情况下,你的时间表延迟现在变得严重了。为了确保获得精确的绩效衡量信息。你应该: 
A.发布时间表更新信息 
B.重新设计时间表基线 
C.设计一个主时间表 
D.准备提出变更请求
【单选题】:      

3题:Once the logic of a network is laid out, the project manager will conduct a forward pass and backward pass through the network. This will provide information on the _____ and identification of the _____ . 
A Slack for each activity, critical path. 
B Slack for each activity, high risk activities. 
C Manpower shortages, high risk activities. 
D High risk activities, non-critical paths. 
E Manpower availability, contingency plans. 
【单选题】:        

4题:凡建设单位征用土地,必须根据()办理申请手续。  
A、集体的有关要求  
B、国家的有关规定和要求  
C、征地企业的有关规定  
D、公民个人的有关要求
【单选题】:      

5题:以下哪句话最好地描述了适合项目管理专业人员的国际项目管理学会行为守则?PMI’s code of conduct for PMPs
A.最优先安排成果质量管理。
B.制定精确的进度计划,包括与主要风险相连的应急方案。
C.坚持和遵守项目的范围和目标。
D.以同等重要性和关注程度管理成本、进度计划和质量。
【单选题】:      

 