根据网考网考试中心的统计分析,以下试题在2018/5/30日PMP考试习题练习中,答错率较高,为:95%
【单选题】the work breakdown structure (wbs) is an excellent tool for objective control and evaluation. which of the following is generally not
validated through the wbs?
a. time, schedule and cost.
b. management coordination and organization structuring.
c. work methods and accountability.
d. quality of work.
e. risk and impact decision-making.
网考网参考答案:D,答错率:95%
网考网试题解析:
暂时没有解析查看试题解析出处>>