根据网考网考试中心的统计分析,以下试题在2018/8/7日PMP考试习题练习中,答错率较高,为:34%
【单选题】which phase of the project life cycle typically has the highest uncertainty and risk associated with it?
a. concept
b. development
c. execution
d. conclusion
e. all of the above.
网考网参考答案:A,答错率:34%
网考网试题解析: