1题:关于规划编制的社会参与和论证制度,下列说法错误的是(    )。
A.为提高规划的科学性,要充分发挥专家的作用
B.规划编制的社会参与和论证制度能保证规划的科学性、合理性 
C.规划编制的社会参与和论证制度充分体现了人民当家作主的权力 
D.对所有规划,规划编制部门都应当公布规划草案或者举行听证会,听取公众意见


【单选题】:      

2题: Earned value technique(EVT)is a tool and technique to measure project performance. In EVT, BCWP refers to ______ .
A.physical work actually accomplished, including the estimated value of this work
B.physical work scheduled to be performed, including the estimated value of this work
C.actual cost incurred to accomplish the earned value
D.none of the above
【单选题】:      

3题:为了拟定沟通管理计划,您首先应当进行的工作是什么?
A 沟通技巧分析
B 组织结构分析
C 沟通需求分析
D 信息技术可用性分析
【单选题】:      

4题:which phase of the project life cycle typically has the highest uncertainty and risk associated with it?
a. concept
b. development
c. execution
d. conclusion
e. all of the above.
【单选题】:        

5题:Which of the following are included in the Acquisition phase(s) of the project life cycle. 
A concept and development 
B development and planning 
C execution and phase-out 
D planning and implementation 
E concept and planning 
【单选题】:      

 