PMP习题练习

PMP考试易错题(2018/10/9)
1题:( )的情况说明国民经济评价可行。
A、经济内部收益率大于社会折现率
B、经济内部收益率等于社会折现率
C、经济净现值大于或等于零
D、财务内部收益率大于基准收益率
E、财务净现值大于零
【多选题】:        

2题:修订根据实际可提供之资源的进度计划的过程被称为资源:
A、划拨。
B、增加。
C、安排。
D、平衡。
【单选题】:      

3题:估算活动资源过程的输出包括()。
A.资源价格
B活动持续时间估算
C.资源分解结构
D出版的估算数据
【单选题】:      

4题:One of your project team members has made a technological breakthrough on an r & d project. the result will be new business for the
company, as well as a company patent. the team member received a company bonus. the motivational strategy used here is:
a. job enrichment
b. linking pay and performance
c. behavior modification
d. freedom in the work place
e. all of the above
【单选题】:        

5题: The major processes of risk management are______.
A.planning,identification,documentation,and assessment
B.identification,planning,evaluation,response development,mitigation,and documentation
C.identification,response development,assessment,and documentation
D.planning,identification,qualitative analysis,quantitative analysis,response planning,and monitoring and control
【单选题】:      

 

您正在结束答题

请确认是否提交试卷?

继续做题 确认提交