【单选题】Although an output of the various control
processes, corrective action is also an input to
project plan execution because it—
A. Ensures that project objectives are met
B. expedites actions to ensure that activities are
completed on time
C. Completes the feedback loop needed to ensure
effective project management
D. Involves performing a planned response for a
specific project risk event
网考网参考答案:C,答错率:55%