【单选题】Although an output of the various control  
processes, corrective action is also an input to  
project plan execution because it—
A. Ensures that project objectives are met
B. expedites actions to ensure that activities are  
completed on time
C. Completes the feedback loop needed to ensure  
effective project management
D. Involves performing a planned response for a  
specific project risk event

网考网参考答案:C,答错率:55%