第1题:在某个软件开发项目中,卖方已经按照合同要求圆满地完成了项目工作。这时,买方又要求在合同中添加一项新工作。鉴于上述情况,卖方应该如何做 ( )
|
【单选题】: |
第2题:定义活动过程所得到的最终成果是( )。
|
【单选题】: |
第3题:在以下哪种情况下,关键路径上的活动可能出现负的浮动时间?() A.用顺推法所得到的完工日期晚于客户所要求的完工日期 B.用逆推法所得到的完工日期晚于客户所要求的完工日期 C.用顺推法所得到的完工日期早于客户所要求的完工日期 D.用逆推法所得到的完工日期早于客户所要求的完工日期 |
【单选题】: |
第4题: In considering project stakeholders, the project management team must do all of the following EXCEPT: A.As much as possible, create conflicts among stakeholders to allow the project team to get its work don B.Identify the stakeholder C.Determine stakeholders requirements and expectation D.To the extent possible, manage stakeholders influence in relation to the requirements to ensure a successful projec |
【单选题】: |
第5题:Although an output of the various control processes, corrective action is also an input to project plan execution because it— A. Ensures that project objectives are met B. expedites actions to ensure that activities are completed on time C. Completes the feedback loop needed to ensure effective project management D. Involves performing a planned response for a specific project risk event |
【单选题】: |