根据网考网考试中心的统计分析,以下试题在2018/12/9日PMP考试习题练习中,答错率较高,为:90%
【单选题】A project is defined as:
A a coordinated undertaking of interrelated activities directed toward a specific goal that
has a finite period of performance.
B a large, complex undertaking with many objectives, multiple sources of funding, and a not
discernible end point.
C an undertaking of interrelated activities directed toward a specific goal that can be
accomplished in less than one year.
D a group of activities headed by a project manager who has cradle-to-grave cycle
responsibility for the end product.
E All of the above.
网考网参考答案:A,答错率:90%
网考网试题解析:
暂时没有解析查看试题解析出处>>