PMP考试

解析:At the end of the closing process

来源:网考网PMP 所有评论

【单选题】 At the end of the closing process group,______.
A.it is verified that the defined processes are completed within all the process groups to close the project phase
B.it is determined that the product of the project is completed satisfactorily
C.project management plan is written off by the project sponsor
D.new change requests are initiated as required

网考网参考答案:A
网考网解析:

[解析] 在项目收尾过程组的最后,______。 A) 应核实定义的所有过程组的过程已完成,来结束项目阶段 B) 应确定项目的产品被满意地完成 C) 项目管理计划被项目出资人取消 D) 新的变更请求被启动 查看试题解析出处>>

相关推荐

发布评论 查看全部评论