PMP习题练习

PMP考试易错题(2019/1/19)
1题:在管理项目时,你发现预计的项目完工时间将超出期望的日期,你首先应该( )。
  • A.向项目增加资源
  • B.评估同时进行更多活动的可能性
  • C.向管理层要求延长工期
  • D.对项目进行赶工



【单选题】:      

2题:Scheduling is the process by which decisions are made concerning: 
A Tasks to be accomplished. 
B Personnel/organization that will be assigned to accomplish the task. 
C Time when the tasks are to be completed. 
D All of the above. 
E A and C only.
【单选题】:        

3题:有效的风险管理首先要求( )。
A.为决策提供明晰的信息
B.所有风险已被确认
C.指派项目经理对确认的风险过程进行管理
D.建立和贯彻风险管理方针
【单选题】:      

4题:A technical requirement has which of the following characteristics: 
A easy to understand 
B a communication tool between the user and the design team 
C written in non-technical language 
D developed in cooperation with the user 
E typically describe physical dimensions and performance requirements
【单选题】:        

5题:the net present value of $110 one year from now at 10% is:
a. 100
b. 120
c. 121
d. $100 less taxes
e. $100 less taxes and interest
【单选题】:        

 

您正在结束答题

请确认是否提交试卷?

继续做题 确认提交