1题: Which of the following statements is true about the WBS
A.The WBS is a deliverable oriented hierarchical decomposition of the work to be executed by the project team, to accomplish the project objectives and create the required deliverable
B.The WBS is an unstructured list of activities in chart for
C.The WBS is the same as the organizational breakdown structur
D.The WBS refers to the bill of material
【单选题】:      

2题:he scope baseline once established and approved, is used: 
A as the basis for making future decisions. 
B to accomplish verification measures. 
C to evaluate potential changes. 
D All of the above. 
E A and C only.
【单选题】:      

3题:下列选项中,___不属于项目的基本特征。 
A.独特性
B.实践性
C.目的性
D创新性
【单选题】:      

4题:techniques that can improve communication include:
a. establishing a single, one-way communications channel
b. avoiding face-to-face communication
c. using redundancy (i.e. saying it two different ways) whenever possible
d. disregarding the sensitivity of your receiver
e. all of the above.
【单选题】:        

5题: When there is uncertainty associated with one or more aspects of the project.one of the first steps to take is to______.
A.revise project plan
B.conduct a risk benefit analysis
C.conduct a needs analysis
D.increase the estimated cost of the project
【单选题】:      

 