PMP考试易错题(2019/2/16) |
第1题:对于( )通货膨胀,调节和控制社会总需求是个关键。 A.结构调整型 B.结构失调型 C.需求拉动型 D.供求混合推动型 |
【单选题】: |
第2题: A、team member notices the project manager that a quality measurement for the project can not be met. What should the project manager do A、Notify management. B、Hold a team meeting. C、Look for alternative ways to meet the quality level. D、Ask management tp come up with options. |
【单选题】: |
第3题:党的十六届五中全会提出我国要“加快建设资源节约型、( )社会”。 A.劳动密集型 B.环境友好型 C.经济集约型 D.科技先进型 |
【单选题】: |
第4题: 在项目型组织中,全职项目团队成员的比例通常是( )。
|
【单选题】: |
第5题: Quality control involves monitoring specific project results to determine if they comply with relevant quality standards. To evaluate quality control outputs, the project team should definitely have a working knowledge of ______ . A.prevention and inspection B.sampling and probability C.special causes and random causes D.tolerances and control limits |
【单选题】: |