根据网考网考试中心的统计分析,以下试题在2019/2/20日PMP考试习题练习中,答错率较高,为:71%
【单选题】The purpose of a dummy activity in an activity-on-arrow diagram is to:
A Identify a task that could be replaced by another.
B Take the slack time into account.
C Show a task that is not necessarily needed.
D Denote a milestone.
E Show a dependency relationship.
网考网参考答案:E,答错率:71%
网考网试题解析:
暂时没有解析查看试题解析出处>>
发布评论 查看全部评论